August 31, 2012

Half of our construction projects are now complete: the universally accessible restroom, complete with changing table, and our new red roof.  Work on the South Wall will be completed by the end of August, which will finally make the exterior of our Church water tight.  The lifts did not pass their inspection because the installation did not conform to the permit.  We will hire a Structural Engineering firm to help us draft a variance request to the State on how the lifts are braced.  Giving toward the Building Fund now stands at $103,730.79 on our way to Through July, contributions for building construction have averaged $3,100/month and our monthly mortgage on the loan is $2,073/month.  A big THANK YOU for your generous contributions.